Stay up to date with notifications from The Independent

Notifications can be managed in browser preferences.

Defence delays add cost and risk

Colin Brown
Tuesday 23 May 1995 23:02 BST
Comments

BY COLIN BROWN

THE fighting capability of Britain's armed forces is being put at risk by delays in projects which are costing the taxpayer an extra pounds 645m, according to a powerful public spending watchdog.

The National Audit Office says more than 90 per cent of the MOD's major projects had failed or were likely to fail their completion dates.

It challenged a report by the MOD showing that the overall cost of 25 projects was likely to be pounds 1.6bn less than forecast. When two exceptionally large projects - for the Trident nuclear weapon system and the Eurofighter 2000 were excluded - there was an increase in the forecast for MOD spending of pounds 645m. But the NAO warned that the delays were also leading to "older less capable equipment" being kept in service for longer than planned.

Delays in computer software to run warship command systems had forced the MOD to limit deployment of type 23 frigates. The NAO says: "The deployment of type 23 frigates without the first three phases of software of the type 23 command system carries significant military risk."

Other major defence projects which had been delayed included the the Spearfish torpedo, now six years behind schedule and requiring the MOD to run the Tigerfish torpedo for longer than planned.

The armed forces were using Clansman combat radios, based on 1960s radio technology, because its replacement, codenamed Bowman, was over four years overdue. It is costing pounds 200m to keep the Clansman system in service.

Delays of two years in the Eurofighter 2000 project had forced the MOD to extend the life of the Tornado F3 in an air defence role and Jaguar in a strike role beyond their original out-of-service dates. Neither is as effective as technologically more advanced Eurofighter.

MOD officials will face a grilling over the report by the NAO next month at a hearing of the Public Accounts Committee of the Commons.

9NAO MoD major projects report 1994; HC 436; HMSO; pounds 13.25.

Join our commenting forum

Join thought-provoking conversations, follow other Independent readers and see their replies

Comments

Thank you for registering

Please refresh the page or navigate to another page on the site to be automatically logged inPlease refresh your browser to be logged in