Another radioactive leak discovered at Fukushima nuclear plant as storage tank overflows allowing toxic water to flow into Pacific

Leak causes yet more problems for under fire Tokyo Electric Power Company

John Hall
Tuesday 08 October 2013 16:28 BST
Comments

A storage tank at Japan’s stricken Fukushima nuclear plant has overflowed, allowing hundreds of litres of toxic water to flow into the Pacific Ocean.

Workers for the Tokyo Electric Power Company (Tepco) discovered the latest radioactive leak during a routine patrol of the site, with the oft-criticised estimating that around 430 litres of the water had already escaped. Official Masayuki Ono said he could not deny that water containing highly radioactive doses of strontium may have flowed down a drain that leads directly into the Pacific Ocean.

The amount of radioactive water involved in the new leak is small compared to the thousands of tons that have escaped since a massive earthquake and tsunami wrecked the Fukushima nuclear plant in 2011. It is, however, the latest in a long line of errors Tepco has made as it struggles to manage a seemingly endless flow of contaminated water on the site.

The tank in question is one of about 1,000 erected on the grounds around the plant to hold water used to cool the melted nuclear fuel in the broken reactors. TEPCO said the water then spilled out of a concrete barrier surrounding the tank and believed that most of it reached the sea via a ditch next to the river.

The new leak will add to public concern and criticism of TEPCO and the government for their handling of the Fukushima nuclear crisis.

In August, the utility reported a 300-ton leak from another storage tank, one of a string of leaks in recent months. That came after the utility and the government acknowledged that contaminated groundwater was seeping into ocean at a rate of 300 tons a day for some time.

TEPCO spokesman Masayuki Ono told an urgent news conference that the overflow occurred at a 450-ton tank without a water gauge and standing on an unlevel ground, slightly tilting toward the sea.

The tank was already nearly full, but workers pumped in more contaminated water into it to maximize capacity as the plant was facing a serious storage crunch. Recent rainstorms that flooded tank yards and the subsequent need to pump up and store contaminated rainwater also added to the shortage, he said.

“We could have, and should have, prevented the overflow,” he said.

Chief Cabinet Secretary Yoshihide Suga said efforts to stop leaks were still insufficient, but defended TEPCO for detecting the problem more quickly than the last time.

TEPCO said the tank and four others in the same area were already filled up to 98 percent of its designed capacity, as in many other tanks elsewhere on the plant.

Tetsuro Tsutsui, an engineer and expert of industrial tanks, said the latest problem was emblematic of how TEPCO runs the precarious plant. He said it was “unthinkable” to fill tanks up to the top, or build them on a tilted ground without building a level foundation.

“That's only common sense,” Tsutsui, also a member of a citizens group of experts proposing safety measures for the plant. “But that seems to be the routine at the Fukushima Dai-ichi. I must say these are not accidents. There must be a systematic problem in the way things are run over there.”

Experts have faulted TEPCO for sloppiness in its handling of the water management, including insufficient tank inspection records, lack of water gauges, as well as connecting hoses lying directly on the grass-covered ground. Until recently, only one worker was assigned to 500 tanks in a two-hour patrol.

In recent meetings, regulators criticized TEPCO for even lacking basic skills to properly measure radioactivity in contaminated areas, and taking too long to find causes in case of problems. They also have criticized the one-foot (30-centimeter) high protective barriers around the tanks as being too low.

So far, the leaks have occurred in easy-to-assemble rubber-seamed tanks that TEPCO had built quickly to accommodate swelling amounts of contaminated water, and the plant has promised to replace them with more durable welded tanks, which take more time and cost more to build. TEPCO has been criticized for building shoddy tanks to cut cost.

“As far as TEPCO people on our contaminated water and sea monitoring panels are concerned, they seem to lack even the most basic knowledge about radiation,” said a Nuclear Regulation Authority commissioner Kayoko Nakamura, a radiologist.

“I really think they should acquire adequate expertise and commitment needed for the job,” she said.

Join our commenting forum

Join thought-provoking conversations, follow other Independent readers and see their replies

Comments

Thank you for registering

Please refresh the page or navigate to another page on the site to be automatically logged inPlease refresh your browser to be logged in